GX Strategic Areas to Spark Data Center Growth and Regional Revitalization
October 5, 2026

BY GILLIAN SAWYER

KIX12, Minoh. Photo by Alex Farrell
KIX12, Minoh. Photo by Alex Farrell.

A new wave of large data centers could begin construction across regional Japan by 2030, as the government moves from identifying candidate sites to preparing land, power and communications infrastructure for future AI and cloud demand. 

METI’s first GX Strategic Area designations, announced last month, cover nine prefectures and 10 locations selected for data-center (DC) cluster development. The goal is to create new computing hubs outside the traditional concentration in Tokyo and Osaka, where available land and grid capacity are already highly limited. 

The timetable is deliberately phased. METI’s selection criteria favor areas where roughly 30 hectares or more of industrial land can be assembled within a 10-kilometer radius, with land preparation preferably completed within about three years and further expansion possible thereafter. At the same time, electricity supply should be capable of scaling over the longer term toward GW-class levels, with around 10 years cited as an illustrative timeframe. 

That means the first projects do not have to wait for an entire GW-scale cluster to be built. In the more advanced locations, data-center construction could begin before the end of the decade, while grid capacity, generation and surrounding infrastructure continue to expand around them. 

The dramatic rise in power demand is expected to be met by building new decarbonized energy sources. Clean power sites, such as nuclear and large-scale renewables, are scattered unevenly around the country. By co-locating high-power-demand industries near such sources, officials hope to improve efficiency, reduce grid bottlenecks, and strengthen energy and IT security. 

If successful, this policy would catalyze domestic and foreign investment in DCs and other AI-related facilities, while also creating the conditions for new industrial and IT clusters outside Japan’s biggest cities.

See Full Report

BY GILLIAN SAWYER A new wave of large data centers could begin construction across regional Japan by 2030, as the government moves from identifying candidate sites to preparing land, power and communications infrastructure for future AI and cloud demand.  METI’s first GX Strategic Area designations, announced last month, cover nine prefectures and 10 locations selected […]